Specific logistic and construction process data is also entered via the Excel Workbook, for example the number of joints welded per hour, the number of pipes bent per hour, the length of ditch that can be cut per hour, etc. The model includes options of multi-jointing at the port area or at the pipe dumps, with any number of joints welded. It is also possible to deselect activities, for example ditching, lower and lay if the pipeline is not to be buried.
The model includes the ability to define construction shift patterns and terrain factors that alter the process rate of certain construction process, e.g. ROW, trenching, etc. while in the defined terrain section.
WITNESS has graphical animation capabilities and it is possible to view the simulation process and progress to understand the issues. The activity icons continuously indicate their state i.e. yellow represents idle, green is busy, red is broken down, magenta means the process is blocked (constrained), etc. As the simulation runs the utilisation of each process is tracked together with progress rate and costs. The model also tracks the number of joints at each location and the number of trucks in use throughout the simulation period.
BP has used this approach to plan and support the construction of the In Salah Gas Export Pipeline Project in Algeria and is currently developing a model for Shah Deniz Gas Export Pipeline Project in Azerbaijan. The In Salah model considers only the logistics of pipe supply from three separate pipe mills to stringing activity to track stock levels and shortages, truck utilisation, determine trigger points for contingency actions, etc. It is possible to define the pipe quantities and production rates for the three separate mills for the three sizes of pipe required, together with options for coating local to the pipe mill or coating ´out of country´ and associated batched shipping operations. The model includes trucking of pipe from port of entry or in-country mills to a multi-jointing yard for campaign jointing of the three different pipe diameters and three different manufactures takes place.
The modelling approach outlined above was initially developed for research and development parametric studies but rapidly became recognised by the BP project groups as a powerful project logistics optimisation tool. For each application, the model is modified to reflect the actual characteristics of the planned construction process.
|